On a fix and flip loan, the rehab budget is financed — but it is released in stages, called draws, as work is completed and verified. Understanding that cycle before you start demo is the difference between a smooth project and a month of stalled work.

A draw is a reimbursement for work already done

The most common misunderstanding is that the rehab money is working capital you can spend ahead of the project. It isn't. A draw releases funds against work that is finished and inspected — you or your contractor front the cost of that portion, then get reimbursed when it's verified.

Practically, that means you need enough liquidity to run a few weeks ahead of the lender. Contractors who expect to be paid the day they invoice, while the draw takes a week to clear, are a frequent source of friction. Agree on payment timing with your contractor before you sign the build contract.

The budget becomes the schedule

Before closing, the scope of work is broken into line items — roof, HVAC, kitchen, flooring, permits, labor — and those line items are grouped into a draw schedule. A typical residential flip has somewhere between four and six draws, tied to milestones like completion of rough work, drywall and paint, and final.

Two buckets matter here. Soft costs like permits, plans, and dumpsters are usually released at closing or with the first draw. A contingency line, often 10% to 15% of the budget, exists for what you find behind the drywall — keep it for that, not for upgrades.

The inspection cycle

When you need money, you submit a draw request listing the line items you're billing for. An inspector visits, confirms the work is in place and matches the scope, and the funds are released, typically within a few business days of the approved inspection.

Photograph everything — before, during, and after each phase — and keep receipts for materials. Documentation is what turns a request into a release without a back-and-forth.

Why draws get held up

  • Work billed ahead of completion — a line item has to be finished, not started.
  • Unpermitted work. If a permit was required and isn't pulled, the lender can't verify what an inspector can't see.
  • Missing photos, receipts, or lien waivers from subcontractors.
  • Change orders nobody approved. Anything outside the original scope needs to be papered before it's funded.
  • A line item that quietly became a different, more expensive line item.

Interest follows the money you've actually taken

Hard money interest is charged on the outstanding balance, so an undrawn rehab budget isn't costing you interest. That cuts both ways: slow draws mean lower interest, but they also mean a longer project, which is usually the more expensive problem on a 12 to 24 month loan.

Some rehab and construction loans build an interest reserve into the loan amount, so monthly payments come out of the loan rather than your pocket. Convenient, but you pay interest on the reserve as well — it is a financing cost, not free money.

Five habits that keep draws moving

  • Use a contractor who has worked with draw-based financing before, and say so in the contract.
  • Hold a real contingency and treat it as untouchable until the project is done.
  • Submit draw requests on a regular cadence instead of waiting until the tank is empty.
  • Keep a single shared folder for photos, receipts, permits, and change orders.
  • Tell your lender early about surprises. A documented problem gets funded; a surprise at the final inspection does not.

Figures are typical residential hard money ranges, not a quote or an offer to lend. Your costs and terms are set by the lender after review.